Hedges Dam Reconstruction

Survey support for Ertech on the full rebuild of the Hedges Dam wall near Boddington, covering machine control models, dam set-out, as-constructed surveys and volume and quantity calculations.

The Hedges Dam reconstruction near Boddington was a complete rebuild of all layers of the dam wall. Existing material was removed and the wall was reconstructed, with the works running from January 2021 to December 2022. Noble Surveys supported Ertech with machine control model creation and upload, dam set-out, as-constructed surveys and volume and quantity calculations.

The works were staged around the existing wall, and different materials had to be quantified after excavation and before placement. Our surveys gave the project team a measured record of each stage, using the same control and design data across machine control, set-out and as-constructed surveys.

Project imagery

Images from the Hedges Dam reconstruction, showing site control, earthworks and the rebuilt layers going in against the existing wall.

GNSS base station on a survey control pillar above the Hedges Dam reconstruction, with a grader working the wall
Earthworks, roller and dozer on the Hedges Dam reconstruction seen from the existing crest
Noble Surveys vehicle at the Hedges Dam reconstruction near Boddington
Sand and rock layers being placed against the existing dam wall at Hedges Dam
Survey instrument set up above geofabric and rock layers during the Hedges Dam rebuild

Scope of work

Survey support from model to as-constructed

Noble Surveys prepared the machine control models the earthmoving fleet worked to, set out the reconstruction, and surveyed the works as material was removed and placed.

  • •Machine control model creation from the design, with models uploaded to the earthmoving fleet.
  • •Dam set-out for each stage of the rebuild, working from site control.
  • •Surveys after excavation of existing material, before new material was placed.
  • •As-constructed surveys of the rebuilt layers.
  • •Volume and quantity calculations for the different materials removed and placed.

Project challenges

Rebuilding a dam wall in stages

Rebuilding every layer of an existing dam wall meant the works had to be staged, and the quantities for each material had to be captured at the right point: after excavation and before the next layer was placed.

  • •A complete rebuild of all layers of the dam wall, removing existing material and reconstructing it.
  • •Staging the works around the existing wall.
  • •Quantifying different materials after excavation and before placement, so each could be measured separately.

Deliverables

  • •Machine control models and uploads for the earthworks fleet.
  • •Set-out for the dam reconstruction works.
  • •As-constructed survey records.
  • •Volume and quantity calculations by material.

Related services & region

Related survey services for similar projects

These services supported the Hedges Dam reconstruction and are commonly used on dam, embankment and earthworks projects.

Peel region project example

Hedges Dam near Boddington shows how Noble Surveys supports Peel region civil and earthworks projects with machine control models, set-out, as-constructed surveys and quantity calculations.